Measure I
Foothill Freeway - Freeway Costs
These costs are for the San Bernardino County portion only
Costs Upland, Rancho Cucamonga, & Fontana Only
Funding Source |
Cost |
|---|---|
Federal |
$74.5 million (15%) |
State |
$54.7 million (11%) |
Measure I |
$332.5 million (70%) |
Other |
$20.3 million (4%) |
Total Cost: |
$482 million |
Costs Rialto & San Bernardino Only
Funding Source |
Cost |
|---|---|
Federal |
$22.4 million (11%) |
State |
$81.3million (35%) |
Measure I |
$118.6 million (51%) |
Other |
$9.5 million (4%) |
Total Cost: |
$232.8 million |
Costs Upland — San Bernardino
Funding Source |
Cost |
|---|---|
Federal |
$96.9 million (14%) |
State |
$136 million (19%) |
Measure I |
$451.2 million (63%) |
Other |
$29.9 million (4%) |
Total Cost: |
$714 million |